INDICATIVE PROJECT TIMELINE

Date Activity
March 2019
  • Peabody acquired the Holloway Prison site from the Ministry of Justice
April – December 2019
  • Technical survey work / site masterplanning / testing options and ideas with Islington Council
January – July 2020
  • Public consultation on draft masterplan and Women’s Building options / engagement with Islington Council and GLA / finalise masterplan
July – September 2020
  • Public consultation on detailed design proposals / continued engagement with Islington Council and GLA / prepare planning application pack
September/October 2020
  • Application submission
Spring 2021
  • Planning committee
Early 2022
  • Start on site
5-7 years
  • Construction period – phased development